Official Blog of the progress of the construction project for Christ Lutheran Church Lake Elmo.
Thursday, June 28, 2012
Construction Update for the week of June 25th – 29th
The excavation of the court yard should be completed. Prep work for the footings of the new basement wall is starting. East Side excavation has started for the new stair tower.
Demolition continues on the upstairs classrooms and the walls and stairs connected to the church.
You should see the new 1500 gallon septic tanks on the East and West side. The tanks will be installed Monday and Tuesday this week.
Unforeseen Conditions - During the excavation courtyard the water line between the kitchen and the education building was broken. Water service was restored to the education building ASAP. The water for the kitchen was restored by Friday.
Staff will be moving over to the 3549 Building next week. Phone service will be restored by July 5th. Thanks for understanding.