Tuesday, June 12, 2012

Update as of June 9th


Update from Jim Lohman as of Monday evening, June 9th
1. Most of the equipment/furniture has been moved into the trailer. The trailer has been moved off the site. Thank you Ron Johnson and his staff for moving the furniture and equipment.  
2. West entrance is now inaccessible. Glass and window frames have been removed and temporary wall is in place. Marv is not sure if the East entrance will be inaccessible for Sunday June 16th. Steve Urtel and Ron Johnson will provide signs on the East and West entrances to notify the congregation to use the North or South entrances.
3. The week of 6/18 - 6/22 the digging for the atrium will start.
4. Ron Johnson will provide me a list of rooms that are vacant so demolition can start. Any furniture or equipment left in the rooms will be considered trash and will go into the dumpster.
5. Rich Sluss is still working with Kyle Katt, City of Lake Elmo to finalize the wording for the letter on the septic tanks 
6. Andrew Naughton will provide new construction schedule and update the final costs for additions and reductions this Wednesday. I will forward the new schedule and costs to the team.
7. I will check with Andrew and Marv regarding the aluminum frames for the windows that have been removed to see if the frames can be recycled. 
8. Hedge on the West side belong to CLC. In order to redo the drive way  the hedge will probably need to be removed. Rich Sluss will talk to the new owners. We are not sure if the house has been sold.
9. Next meeting - We decided that we will meet next Month, July 9th to walk around the construction site. With the construction going we don't have a lot to discuss. We will have weekly updates in the bulletin. We will get back together in the fall to plan the open house. If you have questions or concerns on the construction please call me.
10. Ron Johnson will review the telephone system in the OLD Bank to make sure the move of the Church staff will go smoothly.